7/16/2026 Construction Update for Pleasant Avenue Loop - Zumbrota, MN
Upcoming schedule:
- Trees scheduled for removal will be marked and cut down in the next few weeks for the entire project area.
- Starting in Mid-August the following items will occur in Phase 1 (East 5th Street between 1st and 2nd Avenue and East 2nd Avenue from 5th Street south to the bend in road).
- Phase 1 will be reclaimed (turned to gravel). The roadway will still be passable for local traffic, but delays should be expected while construction equipment shapes and compacts the rock.
- Temporary water lines will be placed and tested. Affected properties will have their water service switched to the temporary lines.
- Sanitary sewer, watermain, and storm sewer will be installed in Phase 1.

Updates are available on the "GoZumbrota" app, City Website, and Email. To be added to the email distribution list please email mraasch@ci.zumbrota.mn.us with subject line "Pleasant Avenue Update"
Project schedule is weather dependent and subject to change.